Stair stringers or risers?

Started by karlperry, May 16, 2020, 05:01:48 PM

Previous topic - Next topic

0 Members and 0 Guests are viewing this topic.

karlperry

I just finished real-world building the shed I designed with all your help, thanks! I've come a long way ...

Now I'm designing a deck in TC2017 Deluxe.

I'm trying to figure out how to create stair stringers or risers. I will cut these from 2x12 material with 7.5" rise and 10.5" run.

I created a 3D box 1.5" wide, 8' long and 11.5" high to represent the 2x12 raw material.
I created a 3D wedge 1.5" wide, 10.5" long and 7.5" tall to represent the stair area. Then I rotated it -35.5378° and moved it to get it precisely oriented to the top edge of the 2x12. Then I duplicated it a bunch of times, lining up the points. The result is a set of stair steps.

To end up with "real" risers/stringers in my drawing I need to cut off the top and bottom at the appropriate places, but I cannot figure out how to make the Slice or Subtract features do what I want. Whenever I try to use them my computer just starts blinging at me.

Can anyone help? I've attached my .TCW file.
Using TurboCAD 2020 Deluxe

DonCW

Quote from: karlperry on May 16, 2020, 05:01:48 PM
I just finished real-world building the shed I designed with all your help, thanks! I've come a long way ...

Now I'm designing a deck in TC2017 Deluxe.

I'm trying to figure out how to create stair stringers or risers. I will cut these from 2x12 material with 7.5" rise and 10.5" run.

I created a 3D box 1.5" wide, 8' long and 11.5" high to represent the 2x12 raw material.
I created a 3D wedge 1.5" wide, 10.5" long and 7.5" tall to represent the stair area. Then I rotated it -35.5378° and moved it to get it precisely oriented to the top edge of the 2x12. Then I duplicated it a bunch of times, lining up the points. The result is a set of stair steps.

To end up with "real" risers/stringers in my drawing I need to cut off the top and bottom at the appropriate places, but I cannot figure out how to make the Slice or Subtract features do what I want. Whenever I try to use them my computer just starts blinging at me.

Can anyone help? I've attached my .TCW file.

Hopefully the attachment makes sense. I deleted the upper deck stringers and started again, the remainder of the drawing was not touched. The top tread is one step down from the deck as shown, create the grid, then the closed polyline tool to outline the stringer. From there an extrude will be possible, then Copy & Paste for the other 2 stringers. I don't have Delux so it's not
possible for me to Save this as a .TCW file for you.
DonCW
2020 Platinum
2018 Platinum
2017 Pro with Light Works Plug in



Windows 10
There's so much to learn and not much time left to learn it.

karlperry

Thanks, Don. I wondered if just using some sort of line tool and then extruding would be best. The grid really helps.

The way the stairs are done on my other deck is that the top step of the stringer is at the level of the top deck. Thus, the first "step" is actually at the same level as the main deck, not down one step height as you illustrated. The benefit is that the top of the stringer attaches to the rim joist, not to one below it. The downside is it is difficult to get to the prescriptive height for a hand rail if that top step protrudes beyond the the top posts. I'll think about using your idea of putting a secondary rim joist board there to hold the top of the stringer. Thanks for that. I have extra room at the back of the deck for the final decking board, so I can just move all the deck boards out 3/4" to make them protrude over the effective block the rim joist produces.
Using TurboCAD 2020 Deluxe

Alvin Gregorio

I went about it a different way karl.

>I drew a 90° 10½"x7½" Polyline.  Then Linear Copied that X=-10½",Y=-7½",20sets.
>Then drew some $Construction Lines to Intersection Snap to to edit the first-most and last-most node of that Polyline, to create the stringer, extra long for now.
>Used the Join Polyline tool, AutoJoining enabled, on all that above.  That created one 2D entity.
>Then activated the Edit (node) Tool, clicked on that Polyline, right-clicked to bring up the Local Menu, and selected "Close".
>Then selected that closed Polyline with the Select Tool, went into its Properties/3D page, and assigned a 1½" Thickness.
>Formatted as a Block, for safe keeping.
>Dragged into Modelspace an insertion of that Block.  Exploded it once, to make it no longer a Block-- it's now just a Polyline with Thickness assigned.
>Used 3D Slice to slice off the amount stringer I didn't want. (actually, I first placed it where it goes on the deck, then 3D_Sliced it)

I did all this in version-21ProPlatinum.  I think that since I made all my 3D elements TcSurface objects-- as opposed to ACIS Solids-- I think it will open with all things intact in your version-2017Deluxe.  I think.  If not, when I "Saved As..." .tcw, in Setup I selected the "Save proxy objects" option, so that Deluxe users can at least see the objects (but not be able to select or edit them).

-Alvin
Alvin Gregorio
TurboCAD: v2024_Plat (31.0.77.1); v2022_Plat; v2020_Plat; v2019_DL; v20.2_PP
Lenovo Thinkpad P20Y laptop; Windows 11 Pro; i7-11800H 2.30GHz, 8-core; 32GB RAM; NVIDIA T1200
3D_Printer: Ender-3 S1 (NOT Pro)

DonCW

Quote from: karlperry on May 17, 2020, 01:47:54 PM
Thanks, Don. I wondered if just using some sort of line tool and then extruding would be best. The grid really helps.

The way the stairs are done on my other deck is that the top step of the stringer is at the level of the top deck. Thus, the first "step" is actually at the same level as the main deck, not down one step height as you illustrated. The benefit is that the top of the stringer attaches to the rim joist, not to one below it. The downside is it is difficult to get to the prescriptive height for a hand rail if that top step protrudes beyond the the top posts. I'll think about using your idea of putting a secondary rim joist board there to hold the top of the stringer. Thanks for that. I have extra room at the back of the deck for the final decking board, so I can just move all the deck boards out 3/4" to make them protrude over the effective block the rim joist produces.

Here is another attachment to consider, with nothing else to move from your drawing as you have it now.
DonCW
2020 Platinum
2018 Platinum
2017 Pro with Light Works Plug in



Windows 10
There's so much to learn and not much time left to learn it.

nikkipollard

It would be nice if stair styles had a stringer option.
Nikki
TC20 platinum, TC 2015 platinum
TC 2017 with lightworks
TC 2021 platinum
Windows 11 Home 22h

Alvin Gregorio

#6
Quote from: nikkipollard on May 19, 2020, 12:29:53 AM
It would be nice if stair styles had a stringer option.

In editions that have the ability (the original poster is using Deluxe), stair stringers would be a good candidate for using Constraints or a Parametric Part Script.
(Heck-- that whole deck that I posted in the Gallery is a good candidate for both of those features.  Particularly for someone that has to draw more than one a month.)
Alvin Gregorio
TurboCAD: v2024_Plat (31.0.77.1); v2022_Plat; v2020_Plat; v2019_DL; v20.2_PP
Lenovo Thinkpad P20Y laptop; Windows 11 Pro; i7-11800H 2.30GHz, 8-core; 32GB RAM; NVIDIA T1200
3D_Printer: Ender-3 S1 (NOT Pro)

nikkipollard


[/quote]

In editions that have the ability (the original poster is using Deluxe), stair stringers would be a good candidate for using Constraints or a Parametric Part Script.
(Heck-- that whole deck that I posted in the Gallery is a good candidate for both of those features.  Particularly for someone that has to draw more than one a month.)
[/quote]

Exactly Alvin. One of the first ppms I made for myself.
But there are advantages to using built in architectural features and it would be nice if the rails were fixed and the stair tool completed.
So that stringers  can be added - or other types of stairs such as concrete or structural steel.